The enterprise-class NYM2 facility in Totowa, New Jersey, is a 200,000-square-foot facility offering 50,000 colocation square feet (CSF), up to 16 MW of power, and 60,000 square feet of work area recovery. This facility is one of several strategic, mission-critical data centers in the New York metro area.
Located just 17 miles from Midtown Manhattan, the NYM2 data center is ideal for primary production and the synchronous data replication requirements of mission-critical applications. This location provides the power, security, and network operations that support and protect mission-critical data and applications.
Address:
50 Madison Road
Totowa, NJ 07512
Water Risk and Use | Now | 2030 Projection | 2040 Projection |
Regional Water Stress | High | High | High |
CyrusOne Water Use | WUE 1.67 L/kWh |
This facility is a legacy site that doesn’t use CyrusOne’s Zero Water Consumption Cooling; therefore, it consumes water like most data centers. We are examining opportunities for reducing water use at this facility.
(Risk assessment and projections based on WRI Aqueduct Tool)
Greenhouse Gases | 2004 | 2007 | 2012 | 2016 | 2018 |
MTCO2/MWh | 0.497 | 0.480 | 0.389 | 0.344 | 0.325 |
Grid Renewables | 2004 | 2007 | 2012 | 2016 | 2018 |
Percent from renewable sources | 3.0% | 2.3% | 3.4% | 4.2% | 5.2% |
This has been increasing by about 0.1% points per year over the last 14 years of published data. Based on US EPA eGRID data for the RFC East subregion (RFCE).